| Cooling Tower Calculations | ||||||||
| Parameter | Units | (Case #1) | (Case #2) | Metric Units | (Case #1) | (Case #2) | ||
| INPUT | Recirculation Rate (RR) | gpm | 6,000 | 6,000 | Recirculation Rate M^3/hr | 6,000 | 6,000 | |
| Delta T (dT) | Degrees F | 10 | 10 | Degrees C | 10 | 10 | ||
| Concentration Ratio (CR) | cycles | 4.0 | 4.0 | cycles | 4.0 | 4.5 | ||
| System Capacity | gallons | 5,000 | 5,000 | M^3 | 5,000 | 5,000 | ||
| Make-Up Calcium | ppm (CaCO3) | 140 | 100 | ppm (CaCO3) | 100 | 100 | ||
| Make-Up Alkalinity | ppm (CaCO3) | 150 | 100 | ppm (CaCO3) | 120 | 100 | ||
| Tower Target Alkalinity | ppm (CaCO3) | 50 | 400 | ppm (CaCO3) | 400 | 400 | FORMULAS | |
| Evaporation Constant (EC) | Typical = .00085 | 0.00085 | 0.00085 | Typical = .00085 | 0.00085 | 0.00085 | Approximately 0.85% of Recirc. Rate is Evaporated per 10 F (5.6 C) Delta T | |
| CALCULATIONS | Evaporation Rate | gpm | 51 | 51 | M^3/hr | 91 | 91 | Evaporation = RR * dT * EC |
| Blowdown Rate (BD) | gpm | 17 | 17 | M^3/hr | 30 | 26 | Blowdown Flow Rate = Evaporation / (CR-1) | |
| Blowdown Rate | MMLB/day | 0.20 | 0.20 | Tons (kg)/Day | 729 | 624 | ||
| Make-Up Rate | gpm | 68 | 68 | M^3/hr | 121 | 117 | Make-Up Flow Rate = Evaporation + Blowdown | |
| Make-Up Rate | gpd | 97,920 | 97,920 | M^3/day | 2,914 | 2,810 | ||
| Tower Calcium | ppm (CaCO3) | 560 | 400 | ppm (CaCO3) | 400 | 450 | Tower Calcium = Make-Up Calcium * CR | |
| Holding Time Index | hours | 3 | 3 | hours | 114 | 133 | HTI = 0.0116 * (Gallons Capacity/ gpm BD) (metric) =0.693*System Capacity/BD Rate | |
| Acid Feed | #/day | 112 | 0 | kg/day | 58 | 31 | Acid Feed = (MU Alk.- (Target Alk./CR))*MU Flow | |
| Acid Feed | Gal/day | 8 | 0 | Liters/day | 33 | 18 | ||